Site plan for a permit in Albuquerque, NM
What Albuquerque's own pages say about sheds, decks and the site plan that goes with the permit, quoted word for word with a link to each page. Then type your address and draw yours to scale for $29.
Can you use our sheet here?
Albuquerque's pages do not say who must draw a site plan. The seal rule does not apply to a house of up to two stories or a garage or similar structure that goes with it, and a homeowner may apply, but the building official may ask for a survey of the lot.
Do you need a permit for a shed in Albuquerque?
Size decides it. A one-story shed or playhouse of 120 square feet or less needs no building permit; a larger one does. A wall or fence under six feet needs a permit from the Zoning Counter, and one over six feet needs a building permit. Even a shed that needs no permit has to meet the zoning rules for where it sits, so it helps to draw it on the lot before you build.
What an Albuquerque site plan should carry
Albuquerque's plan review page asks for the property's location, every existing building with its size and its distance to the property lines, what you propose to build with the same measurements, and the setbacks your zone requires. The code adds the property lines and asks the plans to name the owner and the person who prepared them. Our sheet draws the lot from the county's parcel record, to scale, with each side's length, the lot area, the north arrow and the distances from what you place to each lot line. You add the structure, the existing buildings and the setbacks your zone requires.
Who can draw it
Albuquerque's pages do not say who must draw a site plan. The code's rule for plans sealed by an architect or engineer does not apply to a house of up to two stories or to a garage or similar structure that goes with it, and a homeowner may apply for the permit. The code does let the building official ask for a survey of the lot to confirm where a structure stands; none of the pages we read asks for one up front. The city's handouts for storage buildings and additions are hosted on a server we could not reach directly, so we have not quoted them here.
What needs a permit in Albuquerque
A wall or fence over six feet high needs a building permit; a lower one still needs a permit from the Zoning Counter.
“Walls and fences over six (6) feet high. Note: Walls and fences under six (6) feet require a permit from the Zoning Counter.”
The city's Uniform Administrative Code (the edition published as approved for 2024) exempts low platforms and walks from a building permit. It does not use the word deck, so ask before you count on it for one.
“Platforms, walks, and driveways not more than 30 inches above adjacent grade and not over a story or basement below and not part of an accessible route.”
Sheds that need no building permit
A one-story shed or playhouse of 120 square feet or less needs no building permit.
“One-story detached accessory buildings used as tool and storage sheds, playhouses, and similar uses, provided the building area does not exceed 120 square feet.”
What the site plan must show
The Building Safety plan review page lists what the site plan carries: the property's location, and every existing building with its size and its distance to the property lines.
“All existing buildings (including dimensions and distances to property lines)”
What you propose to build, with its size and its distance to the property lines.
“All proposed additions or structures to the existing building (including dimensions and distances to property lines)”
The setbacks your zone requires.
“Identification of required setbacks”
The code says the site plan shows the property lines and every building on the lot.
“Plans shall also include a site plan showing property lines and the location of the proposed building and of every existing building on the property.”
Plans are drawn to scale, on paper or filed electronically, and name the person who prepared them.
“the house and street address of the work, name and address of the owner, and/or the contractor, and the person preparing the plans”
Who may draw the plan
None of the pages we read says who must draw the site plan. The code requires plans sealed by a New Mexico architect or engineer only outside a list of exceptions, and the list covers a house of up to two stories.
“Single-family dwellings not more than two (2) stories in height.”
The same list covers a garage or other structure of up to two stories that goes with the house.
“Garages or other structures not more than two (2) stories in height which are appurtenant to buildings described in Paragraph 1 and 2 of this subsection;”
The code lets the building official ask for a survey of the lot to check that the structure sits where the approved plan shows it. None of the pages we read asks for a survey with a shed, fence or addition application.
“A survey of the lot may be required by the Building Official to verify that the structure is located in accordance with the approved plans.”
A homeowner may apply for the permit.
“Licensed contractors or homeowners must request permits for the work that will be performed.”
Sheet size
The code sets no sheet size; it asks for plans drawn to scale on substantial paper, or filed electronically.
“Plans shall be drawn to scale upon substantial paper or submitted electronically”
Where to file
Applications and plans go in online through ABQ-PLAN.
“Online - with no need to visit our offices. Visit ABQ-PLAN to apply.”
Before you file
Lot lines are drawn from county GIS records. This is not a boundary survey. Some permit offices require a stamped plan or a survey. Check with yours first. The permit office is City of Albuquerque Planning Department, Building Safety Division. Rules change: the quotes above are what the city's pages said on November 19, 2026.