Seattle says anyone with drafting skills may draw a shed or deck, which rarely needs a stamp. A critical-area lot needs a Washington licensed surveyor's site plan; an addition within 2 feet of the height limit or on steep or landslide ground needs a topographic survey; our sheet cannot stand in. Fits lots up to about 45 by 110 feet.

Do you need a permit for a shed in Seattle?

Usually not for a small one. SDCI's permit page exempts a one-story shed with a roof area under 120 square feet on a slab on the ground; its shed page puts the line at 120 square feet or less and also allows pier blocks or bare soil, as long as the shed is detached, used for storage and not in or near an environmentally critical area. If your shed is exactly 120 square feet, the two pages disagree, so ask SDCI in writing before you build. Any other shed needs a permit, most often a subject-to-field-inspection permit, and a shed over 750 square feet or with beams spanning more than 14 feet needs a full addition or alteration permit. A deck needs a permit once it stands more than 18 inches above the ground. A permit-exempt shed still has to meet the zoning rules.

Where a shed or deck can go

SDCI's shed page says that in the neighborhood residential zones a shed usually cannot sit within 10 to 15 feet of the front property line or within 5 feet of a side property line, it can go in the rear 10 to 15 feet of the yard, and it cannot be taller than 12 feet. A deck more than 18 inches above the ground cannot sit within 10 to 15 feet of the front line, within 3 to 5 feet of a side line, or within 5, 10 or 15 feet of the rear line, depending on how many units are on the lot. A deck more than 36 inches high counts toward lot coverage. Check the Land Use Code for your zone before you fix the spot, and mark the distances on the plan.

What a Seattle site plan should carry

SDCI's site plan tip (Tip 103, updated August 20, 2025) asks a basic site plan for the address, the legal description, the King County parcel number, a north arrow pointing to the top of the sheet, the property lines with their lengths, every existing and proposed structure, the front, side and rear distances from each structure to the lot lines and between structures, the streets and alleys by name, and the driveways and paved areas. If the work touches protected trees, the tip asks for those trees and their protection areas too. Our sheet draws the lot from the county's parcel record, to scale, with each side's length, the parcel number, the north arrow and the distances from what you place to each lot line. You add the legal description, the existing buildings, the driveway and any trees the tree code covers.

Who can draw it

SDCI's shed and deck pages say anyone with drafting skills may prepare the drawings, or you may hire a professional; they also say those drawings rarely need an architect's or engineer's stamp. A deck's structure still has to meet the code, and SDCI may ask for an engineer's design for things like a glass guardrail. Some lots need a surveyor, and our sheet cannot stand in for one. If your lot has an environmentally critical area, such as a steep slope, wetland or flood-prone area, the site plan must be prepared and stamped by a Washington licensed surveyor. For new construction and additions, SDCI asks for a topographic survey with corner stakes and all property lines when the building comes within 2 feet of the maximum allowed height, or on a critical-area site, where grading plans are required. It asks for one in a steep-slope, potential landslide or known landslide area too, unless SDCI grants a modification to submittal requirements or an exemption for simple projects: in SDCI's words, "Topographic survey is not required if you apply for and are granted a modification to submittal requirements or are granted an exemption for simple projects." If your lot does not slope evenly, a licensed surveyor may have to plot the contour lines.

Sheet and scale

SDCI's plan standards tip (Tip 106) asks for PDF sheets of at least 11 by 17 inches, a scale that is stated and drawn as a bar, printed text of at least 10 point, and a blank space for the approval stamp in the same spot on every sheet, about 4.5 by 1 inches or 2.5 by 2.5 inches, preferably in the lower right corner. Our Seattle sheet leaves a blank 2.5 by 2.5 inch space in its upper right corner, inside the title block, which Tip 106 allows. Its minimum scale for house projects is a quarter inch to the foot. Our Seattle sheet prints at an eighth of an inch to the foot, which is below that minimum. It relies on Tip 106's note that SDCI "may allow" a smaller scale in certain cases, and an eighth of an inch to the foot is the scale of the sample site plan in SDCI's Tip 103. If you want certainty before you order, ask SDCI in writing whether that scale is accepted for your project. An eighth of an inch to the foot is 1 inch = 8 feet, and our sheet draws every Seattle lot at that scale. On an 11 by 17 sheet it fits a lot up to about 45 feet wide by 110 feet deep, or about 60 feet square. A larger lot is refused at the address step, before you pay.

What needs a permit in Seattle

A deck needs a permit once it stands more than 18 inches above the ground, sits on a roof, or is in an environmentally critical area.

“You need a permit to build a deck if it is: More than 18 inches above the ground”

The city's page, read November 19, 2026

A shed that misses any of the exemption conditions needs a permit, usually the quicker subject-to-field-inspection kind.

“All other sheds require a permit; most require only a subject-to-field-inspection permit.”

The city's page, read November 19, 2026

Any exterior work, a new shed, deck or one-story addition included, is filed with a site plan.

“You need to submit a site plan when you change the outside of your house or accessory structure, or when you do exterior work on your site.”

The city's page, read November 19, 2026

Sheds that need no building permit

SDCI's permit page exempts a one-story shed with a roof area under 120 square feet on a slab on the ground.

“A one-story detached accessory building such as a greenhouse, tool or storage shed, playhouse, or similar building if the projected roof area is less than 120 square feet and the building foundation is only a slab on the ground”

The city's page, read November 19, 2026

SDCI's shed page puts the line at 120 square feet or less, and also allows pier blocks or bare soil, if the shed is one story, detached, used for storage and not in or near a critical area.

“The total area (or “footprint”) of the shed’s roof is 120 square feet or less.”

The city's page, read November 19, 2026

What the site plan must show

The site plan shows every structure to scale and where the new work sits against the property lines.

“Your site plan must show all structures to scale and clearly show where the work will take place in relation to existing features and property lines.”

The city's page, read November 19, 2026

The distance from each property line to the nearest point of the structure.

“show the distance from each property line to the closest point of the structure.”

The city's page, read November 19, 2026

The legal description of the property.

“Legal description of the property.”

The city's page, read November 19, 2026

The King County parcel number.

“King County Assessor's parcel number (property tax account number).”

The city's page, read November 19, 2026

A north arrow pointing to the top of the sheet.

“North arrow pointing to the top of sheet.”

The city's page, read November 19, 2026

The property lines with their lengths.

“Property lines and dimensions (existing and proposed).”

The city's page, read November 19, 2026

Front, side and rear distances from each structure to the lot lines, and the distances between structures, porches and decks.

“For existing and proposed structures, the front, side and rear distances from the structures to the property lines, and distances between structures, porches and decks.”

The city's page, read November 19, 2026

The streets and alleys next to the lot, by name.

“Right-of-ways, including adjacent street(s) name(s) and alleys.”

The city's page, read November 19, 2026

Driveways, parking and other paved areas, existing and proposed.

“Location and dimensions of all driveways, parking areas, and other paved areas (existing and proposed).”

The city's page, read November 19, 2026

Who may draw the plan

SDCI's shed page says anyone with drafting skills may prepare the drawings for a shed.

“Anyone with drafting skills may prepare the drawings or you may hire a professional to help you.”

The city's page, read November 19, 2026

Its deck page says the same for decks.

“Deck drawings rarely require a professional’s stamp indicating they were designed by an architect or engineer. Anyone with drafting skills may prepare the drawings, or you may hire a professional to help you.”

The city's page, read November 19, 2026

On a lot with an environmentally critical area (a steep slope, wetland or flood-prone area, for example), the site plan carries extra items and must be prepared and stamped by a Washington licensed surveyor.

“Numbers 23-29 are additional items required for an environmental critical area site plan and must be prepared and stamped by a state of Washington licensed surveyor.”

The city's page, read November 19, 2026

On a lot that does not slope evenly, a licensed surveyor may have to plot the contour lines.

“Note: For building sites that do not slope uniformly and gradually, a licensed surveyor may have to plot the contour lines.”

The city's page, read November 19, 2026

For new construction and additions, SDCI's plan requirements tip asks for a topographic survey with corner stakes in three cases: the building comes within 2 feet of the maximum allowed height, grading plans are required because the site is a critical-area site, or the site is in a steep-slope, potential landslide or known landslide area unless SDCI grants a modification or a simple-project exemption.

“Topographic Survey with corner stakes and all property lines when:”

The city's page, read November 19, 2026

The first case is a building near the height limit.

“Your building is within 2 feet of the maximum allowed height”

The city's page, read November 19, 2026

The second is a critical-area site, where grading plans are required.

“You are required to provide grading plans for ECA sites.”

The city's page, read November 19, 2026

The third is a steep-slope or landslide area, unless SDCI grants a modification or a simple-project exemption.

“Your site is located in a steep slope, potential landslide, or known landslide area. Topographic survey is not required if you apply for and are granted a modification to submittal requirements or are granted an exemption for simple projects.”

The city's page, read November 19, 2026

Sheet size

Plan sets are filed as PDF on sheets of at least 11 by 17 inches.

“Minimum Sheet Size (for plan sets): 11” x 17””

The city's page, read November 19, 2026

For a house project Tip 106 sets the minimum scale at a quarter inch to the foot.

“Scalable with the scale clearly specified and graphically depicted. Minimum scale for single-family, duplex, townhouses, small multifamily, and small commercial projects is ¼”=1’.”

The city's page, read November 19, 2026

Leave a blank space for the approval stamp in the same spot on every sheet, about 4.5 by 1 inches or 2.5 by 2.5 inches, preferably in the lower right corner.

“The space should be approximately 4.5” wide and 1” tall, or 2.5” wide x 2.5” tall (or rotated 90 degrees).”

The city's page, read November 19, 2026

The same tip says SDCI may allow a smaller scale in certain cases.

“Note: In certain cases, we may allow you to use a smaller scale.”

The city's page, read November 19, 2026

SDCI's own sample site plan is drawn at an eighth of an inch to the foot.

“BASIC SITE PLAN (Scale: 1/8" = 1'-0")”

The city's page, read November 19, 2026

Printed text is at least 10 point.

“Minimum Font Size: 10 pt”

The city's page, read November 19, 2026

Where to file

Applications and drawings are filed online through the Seattle Services Portal.

“You need to submit your application materials online through the Seattle Services Portal.”

The city's page, read November 19, 2026

Before you file

Lot lines are drawn from county GIS records. This is not a boundary survey. Some permit offices require a stamped plan or a survey. Check with yours first. The permit office is Seattle Department of Construction and Inspections (SDCI). Rules change: the quotes above are what the city's pages said on November 19, 2026.